Maintenance Strategy - Order Genaration

Hi

In IP11 I have created Maintenance Strategy for Order to generate 1M 4M 6M.

When the Strategy Plan is scheduled Order is getting generated every month (2nd and 3rd month also) and for 4 m and 6m

I would like to have the Order generated only on 1M and then on the 4M and 6M.

Suggestion pls...

Regards

Venkat

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    Posted on Nov 16, 2012 at 05:55 AM

    Hi Venkat its possible . In your startgey use offset .

    Regards

    sap pm

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 16, 2012 at 05:05 AM

    hi

    strategy is used for repeated operation to be performed at frequent interval say every 1 month, every 4 months extra. if you want to create the order on 1st ,4th and 6th month only its not possible either you have to check with user exit it is possible

    Regards

    Thyagarajan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.