Dear experts,
We are in SRM7 ECC6 ehp4, implementing SSP, created a SC after approval PO created with Held status in ECC using "PurchaseOrderERPRequest_Out_V1" but PO number not updated in SRM under related documents.
i could not see any update coming from ECC to SRM once PO is created in Held status, even after changing PO and Ordered still there is no update to SRM.
Am i missing some thing in ECC side, please suggest.
Regards,
Raghu
Hi,
Did you check ECC whether the PO is replicated to ECC or not ? Also, have you set up the background jobs BBP-GET_STATUS2 & Clean_reqreq_up?
Kind regards,
Krish
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Krish,
PO created in ECC in Held status, i ran the BBP-GET_STATUS2 & Clean_reqreq_up but get status2 job failed with error "On the basis of the data, no changes possible"
Since we are in SRM7 ECC6 Ehp4 and activated ESOA i assume an XML should from send ECC, but there is message.
Regards,
Raghu