Hi our test system had a crushed so we try to do

data base copy from the production system .

i follow the stepes from the " how to ... system copy in sap business intelligence system landscape " and notes 325470,325525,151603,131018.

i detach my PRD db attach it to my QA sytem then i did a client copy so i will have my old client number . then i run trans. DBLSS to convert to the QA LSN .

it seems that becuse i had on the PRD system the logical

system name of the QA system i get a lot of error after

runnig DBLSS .

when i run trans. RSA1 to check the connection to the source system i get the error mesage " Logical system name has been changed for this system ".if i connect my old Logical system name i can

run RSA1 but then all my connection to the sourse system are delete .

what i need to do to run RSA1 with my new Logical system name and define the connection to the sourse system .

Amit Zait