Skip to Content
author's profile photo Former Member
Former Member

Mail and perodic budgeting in internal order

Dear Experts,

I have configured internal order planning,budgeting and availability control.

and same is working fine.

but

1) Mail is not flowing to budget manager in case actual exceeded to budgeted .system is throwing error msg.

I have done.

Tolence limit set for 2 Warning with MAIL to person responsible if 80% usuage

and mantain budget manager for the id i have longin against order type/conteolling area and object class.

anything i missed out ? becoz mail is not flowing in sbwp-SAP inbox

and 2)

need to budget peroidic instead of annaully but i will not get perodic option in KO22 tcode .

there i m getting year .if you double click peroid option is not coming.

how to do peroidic budgeting?

regards

SONU

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 15, 2012 at 09:18 AM

    Dear Sonu,

    please check:

    http://wiki.sdn.sap.com/wiki/x/6gLvE

    br, Guido

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 17, 2012 at 07:19 AM

    Dear Experts,

    Pls Advice....

    M i forgot to do anything or anything left out.

    pls guide me.

    regards

    Sonu

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 17, 2012 at 07:29 AM

    Hi Sonu,

    Object Class maintained in the Order type and Maintain Budget Manager should be same, and User name should be in Capital letters.

    Thanks & Regards

    Srinu

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Srinu,

      Thanks for your Reply.

      As you said ..everything is same.

      But I have maintained tolerances setting for internal order type for error and mail to budget manager with 100%.

      System is giving error message if i m trying to post actual more than budgeted but same time system must flow mail to budget manager as per the setting in spro becoz eror and mail % are same.

      is this work.

      regards

      Sonu

  • author's profile photo Former Member
    Former Member
    Posted on Nov 19, 2012 at 04:41 AM

    Hi,

    First you can check in your budget profile activation type is maintained or not under availability control(OKOB).

    Also check in budget manager configuration and order type configuration. Object class assignment is mandatory for both cases.

    Hope this helps you and let me know if any queries.

    Regards,

    Puri

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.