Hueristic run is accumulating demand at end of horizon

Hi

Can anybody help to identify the issue.

when we are taking heuristic run, Its generating current month and next month Preq as per defined lead time and for all balance month demand (from 3rd to 6th month) its accumulating whole preq in last month ie 6th month. If we take run today it will generate Preqs of Nov & dec 2012 and after that in June - July 2013 only.

Thx  in advance!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Nov 15, 2012 at 04:34 AM

    Hello, Maybe you have set period lot size method for your product/location? Please have a look at the 'Lot Size' tab in the master data /sapapo/mat1.