Dear Team,
I am trying to plan for material using MRP Area.
I have done below setting in my ECC system.
1. Create MRP area by SPRO -> MRP -> Master data -> MRP area -> Define MRP area.
Select MRP type 02 - storage location. Enter the plant and receiving storage location. receiving storage location will be used for receipt elements like
planned order, production order etc.
How / where to specify "Issuing storage location" while creating MRP Area?
2. Define scope of planning by tcode OM0E.
In the new entries screen, entered the controller as 333 and entered the MRP Area. Here i have NOT provided the plant.
3. Activate MRP Area in SPRO
4. Create planning file entries in om0f
5. In SPRO -> Define parallel processing in MRP.
6. In MM02 assign MRP area in MRP1 view for the material 612-200.
7. Create the PIR in MD61 for the 612-200 (enter the material number and MRP Area)
8. While MRP run (MD01), enter the "Scope of planning" and select the check box "parallel processing" in the initial screen.
After MRP run, i am expecting that planned order will be created for the finished product "612-200" based on the PIR. But no planned orders generated in MD04. i am seeing only MRP element "IndReq"(LSF) in the MD04.
Can you please guide me to create the planned order for the PIR?
thanks