Confusion in Maintenance Plan Scheduling

Hello everybody,

I'm involved in the SAP implementation for our company, especially in the PM module. I would be grateful if help me calriying a confusion that I'm facing. I will give you my example then I will as my question.

- I have maintennace strategy (key-date) with 1, 3, 6, 12, 24 months packages

- I have created a general task list and assigned the previous strategy to it, and I included one task which is performed every 6 months (twice a year)

- Then, I have created maintenance plan and assigned the previous task list to it. I made scheduling period to be 1 YR and the start up date to be todays date (14.11.2012)

- Finally, I went to scheduling this maintenance plan, and here confusion happens.

After scheudling the maintenance plan, I expected the system to display two calls based on the start up date of the maintenance plan and the operation frequency in the task list

I expected to see two calls:

first one with plan date (14.05.2013)

second one with plan date (14.11.2013)

but the system is only showing one plan date which is the one on (14.05.2013), and doesn't show the other.

now I tried different values for start of cycle for the maintenance plan like I put the cycle to start from yesterday (13.11.2013)

Here the system shows the two expected calls

first one with plan date (13.05.2013)

second one with plan date (13.11.2013)

Can you please clarify the confusion for me. Does the scheduling of the maintenance plan depends on todays date? If it depends, then why the system is asking for start of cycle date? I expected the system should schedule the plan based on the start up date, wethear I start the plan on 01.01.2012, or 01.01.2100

Thank you

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Nov 14, 2012 at 07:08 AM

    hi

    Since you have maintained the scheduling period as 1year i think the system calculates with the present date and hence the 14.11.2013 is invalid hence system behaves the same, you can see the same result for future dates also , system is considering 1year=365 days.

    check with different cycle like 1 month and specify the scheduling period as 2 months and check , system will raise one call object only

    regards

    thyagarajan

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 14, 2012 at 08:00 AM

    What Call Horizon have you used in your maintenance plan (see Scheduling Parameters tab on the plan)?

    Which of the following are you using:

    • Time
    • Time - Key Date
    • Time Factory Calendar

    PeteA

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.