Automatic dispatching in Capacity Requirements Planning

Hello;

Can we make automatic dispatching in capacity requirements planning??

Here is the scenario:

During Capacity leveling, there are some technicians who are overloaded, I need the system to suggest another technicians if they are the with the same qualifications.

Can this scenario be configured in SAP by any means??

Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 14, 2012 at 12:16 PM

    Hi,

    In standard R/3, automatic dispatch is not possible. It has to be done manually through CM25.

    Regards / US

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 14, 2012 at 12:55 PM

    Hello

    You can use transaction CM40 to create a mass processing job for dispatching.

    BR

    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.