Skip to Content
avatar image
Former Member

When running MRP at supplying plant MRP is not considering STR as a requirement

Please help me in this.


When running MRP at supplying plant MRP is not considering STR as a requirement.


Scenario:


Receiving plant : STR is generated during MRP run to supplying plant for 100 quanitity


Supplying plant :


Initial stock is 0

Reorder point 100, fixed lot size 100

MD04 shows STR for 100 qty from receiving plant


When MRP is run at supplying plant , PR is getting generated only for 100 qty to satisfy reorder point.


Ideally isn't the qty in PR should be 200 ( 100 for reorder point, 100 for STR requirement)? Do we need to do any customized settings for this? Can any one help me in this.


Regards

Ranjjini

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 10, 2014 at 09:24 AM

    Dear Ranjjini,

    Please, address your question to SCN PP Space http://scn.sap.com/community/erp/manufacturing-pp/content

    Regards,

    Alex.

    Add comment
    10|10000 characters needed characters exceeded