Hi Guru's,
I have a question regarding SNP stock transfer horizon, or in general timefences within SNP.
Is it possible to create a fix date as the timefence instead of using "dynamic dates" always being i.e. 15 days.
We have products which we do not want to start planning on untill ie. 8th Jan 2013, but from then on it is to be planned without a timefence or SNP stock transfer horizon.
Do you guys now of a possibility to do this?
At the moment we are updating masterdata dayily, withdrawing 1 day every day....
Looking forward to hear from you...