on 11-12-2012 10:59 AM
The plant and Work Center XYZ is assigned a Factory Calendar which is a 7 days .
The Factory Calendar is assigned the Holiday Calendar……and Holiday Calendar has thanksgiving defined as a Holiday.
But this plant is working on thanksgiving date. so how to change it
Please create a new holiday calender and then assign this to a new factory calender which in turn to be assigned to the Plant
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
if several plants share the same calendar and only one is working, then you need a separate calendar for this plant.
otherwise you can just tick the indicator that holidays are workdays, except this is just an exception for Thanks giving, then you would need an extra holiday calendar without thanksgiving which is assigned to an extra plant calendar for your special plant.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.