Dear Experts,
We are in SRM7 SP12 with ECC 6 ehp4, we are implementing SSP in Classic scenario.
while creating SC using a Internal goods for a material, i could not see any Source of supply.
i have maintained the Info record and Contracts for the same material , P.Org and plant combination still i could not see any of them.
Is there any setting required for populating these values.
We already using Sourcing with PDP, now wanted to implement SSP as well for few P.cats.
Thanks in Advance,
regards,
Raghuveer