on 11-12-2012 1:49 AM
Dear Guru,
I got message 61 533 when making a costing run for a mterial.
(while the first step "selection the material"")
2 plants have same configuration in material master, but one didn't have the mssage.
Please let me know if any one knows where I could check to sovle it.
Thanks,
Steven
Detail message as below
===========================================
Special procurement type Z9 not defined
Message no. 61533
Diagnosis
The value you have entered is not defined in the system.
Procedure
Check your entry and choose another value from the possible entries.
If you want your original value to be defined in the system, contact
your system administrator.
Hi,
First you check in material master MRP2 Tab or Costing1 Tab, special procurement type Z9 is not maintained or not.
If not maintained, kindly maintain and check costing run again.
Hope this helps you and let me know if any queries.
Regards,
Puri.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.