Good morning gurus, I have a puzzling question that need assistance on (and if this is not the right place for MRP questions please let me know and I will move this post).
I updated several Purchase Info Records and when MRP ran it did not pick up those changes.
The changes I did were to the Planned Delivery Time (10 days to 1 day). We run MRP every morning with a Net Change Planning (NETCH).
We were eventually able to get MRP to 'see' those materials and re-plan them by running MRP with a Processing Key of Online Regenerative Planning (NEUPL).
So a few questions come out of this:
So why did MRP pick them up when we ran then with NEUPL and not NETCH?
Was there something else I should have selected in the MRP Run (Scheduling, Planning Mode)?
Is a PIR Planned Delivery Time not an MRP Relevant change?
Thank you for your assistance.
~nic