Hi Everyone,

I am trying to identify how to extract Rem Ord Pln value from RPSCO. Though I can see Rem Ord Pln values in Hierachical reports the same is not been mentioned in RPSCO table with Value Type 25.

However if I deduct the actuals and commitments (value type 4, 21 and 22) from the plan value (val type 1) for all orders and networks which are taged to WBS elements it get equls to the Rem Ord Pln value.

If this is a viable way to extract the Rem Ord Pln value from RPSCO?

Regards,

Mark