Hello Experts,

My requirement is regarding MRP run for interchangeable materials.

I have finished Product "A" which can be made from only one raw material "R".

Material "R" can be interchangeable by "R1" , "R2" , and " R3 ". as " R , R1 , R2, R3 " provided by different vendors " V, V1, V2, V3" respectively.

I want to maintain the bom of "A" by considering the "R, R1, R2, R3"

When running the MRP system should consider the stock of all the " Interchangeable " materials and planned the proposals for the finished product.

Note: "Alternate Item concept is not applicable as MRP will not consider stock of interchangeable( Alternate Items) items"

Please Help.

Regards,

Zoneera