using a service contract of different company code in PM order

Former Member
0 Kudos

Hi ,

I have centralised procurement scenario where service contract is created at a centralised coy code say X . My PM order plant belongs to coy code Y . If Itry to use the agreement of coy code X , The system will not allow .

Is there any way to get this working ? .

Regards

NP

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Kudos

NP,

Just to confirm, you mean a CS service contract (TCode VA41/2/3)??

If so, then as with the above posts, its probably not a standard SAP process.

Try opening an OSS Message to SAP to see what they recommend..

PeteA

Former Member
0 Kudos

Hi PeteA

It is MM value contract with services created at central purchase organization which is in company code X ..PM order  is in coy code Y .

In MM you can create PR for differnt plant code by reffereing to centralised agreement (Source list ...)

If these feature exists in MM , PM should also should support centralised procurement

Former Member
0 Kudos

Hi PeteA

It is MM value contract with services created at central purchase organization which is in company code X ..PM order  is in coy code Y .

In MM you can create PR for differnt plant code by reffereing to centralised agreement (Source list ...)

If these feature exists in MM , PM should also should support centralised procurement

Former Member
0 Kudos

Hi ,

I used sap note 32900 to do this .

Answers (1)

Answers (1)

Former Member
0 Kudos

Here you are not assigning Coy code Y to Coy code X. Then in the system, its not possible to have centralized service contract. Each company code will have its own contract even physically its same.

Former Member
0 Kudos

Hi Mahesh ,

I know it is not possible in standard . However if I go through MM route , agreement of different company code  gets refreed from source list automatically . If it can happen in MM through souce list whhy can't this be in PM order

Former Member
0 Kudos

SAP may consider this in future. Or I have not known the feature available currently if the scenario have been mapped in current version.

I have never tried this scenario.

Former Member
0 Kudos

Dear Narasimha,

The cross company function would have been activated in your organisation.

In T.Code:OX18, do not assign company code to plant and try.

James Prabaharan