Need to is there a tight integration between SAP MM and SAP PM. The reason to ask this is, we have typical issue. As per PM process, we create

Equipment

Maintenance Plan for the equipment

Task List

Plant Mainteanance Orders get generated based on Plant (suppose it is monthly). We raise purchase orders for year for service and mainteanace contract, so in this case we cannot maintain the AA category as "F", because I will have monthly new PMO, so I maintained AA categoy as "U", so at the time of service entry sheet user will identify the PMO and entry it.

But requirement from user is system should provide /propose the PMO for that equipement. As there will be lots of equipment and that many PMOs ot will be difficult for user to check it manually. or

At the time of closing of PMO, system should check if any cost is booked or not on this order and then propose service entry sheet for the same.

As there is no direct common point between MM and PM, I do not know how it will happen.

Can any one advise me on the same, in case of any process change required or any enchancement can be done either in PM or in MM

Please advise.