Hi,

I have set batch set at material level

Now i have a question that can i have same batch numbers for two different material in a plant. But it is not possible through internal number assignment and how should we do this

My requirement is say two subassemblies s1 and s2

I should have only two batch numbers for s1 say for eg: S1 has 2 batches x1 and y1

And in the same way for S2 i.e s2 also should have same batch number used for s1 i.e. x1 and y1

In the same way it follows for all subassemblies s3,s4,s5

So while doing GR WITH RESPECT TO PRODUCTION ORDER OF S1 I WILL POST TO EITHER BATCH X1 OR BATCH Y1

How can i map this scenario