on 11-07-2012 6:40 PM
Hello,
We are on EHP5.
When I try to add a requisition into an existing PO in ME22N, the attachment on the requisition item does not get transferred immediately to PO item.
Once I save the change PO, and re-open it in ME23N, i am able to see it in the PO.
This used to work correctly earlier but broke after upgrade to EHP5.
If anybody has an idea on this, please suggest.
Thanks,
Sushil.
SAP released OSS Note 1653977 to solve this issue.
-Sushil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I don't see that this Note 1653977 - ME22N - AM 250 Address error when creating new items has any relation to this discussion
it says "you receive error AM 250 'Invalid value for & in function module &'."
you had not mentioned something like that in your question.
SAP explains in OSS Note 1140398 - Transferring docs from
purchase requsition to purchase order
that this functionality is not available, and yoou can get it with BADI implementation for extra charge.
if you lost this functionality with the upgrade, then I suspect that the SPAU was not done properly, or a new bug came in.
if you interfaced SRM, then check OSS Note 1400088 - SC attachments
transferred to ECC PR are lost on EHP upgrade
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.