Hello all. I have a question that I am unable to find an answer to.
For a customer, we are looking into performing a enhancement package [b]update[/b] on their existing ECC6 system. This system is, at this moment, enhancement package-less. Should not be a problem since we have performed enh. pack upgrades before. However, they have also expressed their wish to have the same system migrated to unicode. If possible, in the same time window.
I have found that during enh. package [b]upgrades[/b], this can be combined using a CUUC (Combined Upgrade and Unicode Conversion). However, since this is not an upgrade but an [b]update[/b] according to SAP (since system is already ECC6), can this CUUC upgrade strategy still be used? Note 928729 isn't really clear about that unfortunately. Thanks in advance!