I have an internal order with budget management activated. Let's say remaining budget is 1000. Then, I create a service purchase order connected to the internal order. I also mention that the service purchase order has no limit for unplanned services.
If I create a service entry sheet for unplanned services for 2000 or Service entry sheet with exceeding amount the amount of budget, will SAP give me an error message saying that budget has been exceeded? Can you set it in the system that service entry sheet will not be posted if budget has been exceeded?
Just a follow up question, is there budget checking for both planned and unplanned services? How do you set this in SAP?