Former Member
Nov 07, 2012 at 06:53 AM

KKS2 variance cost

320 Views

hi,

when enter KKS2, error message No target cost versions exist in controlling area.

may i know if the variance is the difference between actual cost vs target cost? if not target cost, i think will not have such error message. correct?

some told me is actual vs standard cost, some told me actual vs planned. so i just wonder the correct variance is actual vs target.

thanks