Nov 07, 2012 at 06:04 AM

Progress Analysis Problem

44 Views

Hi Friends,

I am getting problem while executing the CNE5 Progress analysis report.

Actually in out project we are using cost element wise cost planning, here i have done the required configuration for progress analysis like,

1.Maintain Progress Version (EV Basis- cost plan active project overall projects POC weighting-cost plan active project overall projects)

2.Define Statistical Key Figure for Percentage of Completion

3.Define Measurement Methods

4.Define Measurement Method as Default Value ( cost proportional for wbs and activity internal processing )

5.Maintain Assignment of Cost Element Group

6.Maintain Statistical Key Figure Groups

7.Assign Statistical Key Figures to Value Categories

After done this i have ran CNE1 report after this i ran CNE5 in this report i am getting progress for activity confirmations like % duration and % work but i am not getting for cost progress .

So, in order to get the BCWP, BCWS, POC results what changes do i need to change

Please suggest me

Thnks,

Srikanth.