Hi Friends,
I am getting problem while executing the CNE5 Progress analysis report.
Actually in out project we are using cost element wise cost planning, here i have done the required configuration for progress analysis like,
1.Maintain Progress Version (EV Basis- cost plan active project overall projects POC weighting-cost plan active project overall projects)
2.Define Statistical Key Figure for Percentage of Completion
3.Define Measurement Methods
4.Define Measurement Method as Default Value ( cost proportional for wbs and activity internal processing )
5.Maintain Assignment of Cost Element Group
6.Maintain Statistical Key Figure Groups
7.Assign Statistical Key Figures to Value Categories
After done this i have ran CNE1 report after this i ran CNE5 in this report i am getting progress for activity confirmations like % duration and % work but i am not getting for cost progress .
So, in order to get the BCWP, BCWS, POC results what changes do i need to change
Please suggest me
Thnks,
Srikanth.