Our client has a plant which is maintained with two factory calendars. The requirement is that the production order for a material needs to be scheduled based on the working days of the Factory Calendar assigned to the Work Center of the Routing. But when I carry out the planning through MPS, the planned orders are generated by skipping the working days of the Work Center Factory Calendar, as these days are maintained as holidays in the Factory Calendar assigned to the plant.
I am also unable to change the finish date in the planned order level, to the valid working days for the work center. Is there a way for the MD41 transaction, to schedule the Material as per the dates in the Work Center Factory Calendar? Thanks!