Hi gurus,
I have this scenario:
- PO with Releae Strategy "XX" and the release step 2/2 and a fraction of € 100 -> ok
- Step in the production of a CR in which you modify strategies. The release strategy "XX" becomes obsolete and is replaced by "XY" (in CL20N the characteristics of the XX are then deleted) -> ok
- The user enters edit ODA and manually enter the flag position "Final Delivery" to set the value to 0 "still open" -> ok
- The system will reset the release strategy and assign ODA strategy XY
PS. the changeability of Purchasing Document During / After Release is enhanced with 4 - Changeable, new release in case of new strat. or val. change
Not being a modification of the ODA, why are reset strategies?
thanks for your help