Hi,
For one particular part, MRP run is not generating the planned order. This material has a safety stock on it and when MRP runs, it would not create the PO. Instead, the available quantity is goin in negative.
Below is the config of the material:
MRP type : PD
Max stock level : 0
Procurement Type : F
Planned del time : 14 days
Service level : 0%
Safety stock : 10
strategy grp: 40
Availability check: 02
Please let me know if you have experienced similar issue and if there is any config to check.
Thanks,
DK