Hi ,
I came across an issue and had trouble finding an explanation , The goods Issue time is being automatically pushed up by an hour if the requested delivery date is the same day as the order and a route schedule is being maintained. I have trouble finding the reason , any suggestions would be greatly appreciated.
For eg -
The order comes in on 11/1/2012 and the material gets confirmed same day 11/1/2012 the route schedule has a gi time of 23:00 but what is happening is the GI time in the order is being pushed up by 1 hour so its falling to the next day11/2/2012.Kindly refer the screen shots .