Nov 02, 2012 at 03:03 PM

PM Order Permits

280 Views

Dear all,

I have created Prmits for PM Orders based on PM order type and total estimated costs of the order.

For e.g when a PM order's estimated costs are up to 1000EUR a person to approve them if it is above 1000 a different person to approve it etc.

I have two questions:

1) Is it possible if a permit has already been issued and the cost of the PM order is changed the Permit to be needed to re-issued. For e.g a permit has been issued for an order up to 1500EUR but the cost is changed to 2500EUR. It is needed the permit to be reversed and needed to be issued again, even if the person to give this issue is the same.

2) I want up to 1000 one person to issue a permit, from 1000-3000 two persons to give the Permit, the 1st one for the 1000 and the 2nd one for the amount above it. So when a PM order is above 1000EUR not a different permit to be needed, but two pemits, the first and the 2nd.

BR