Former Member
Nov 02, 2012 at 09:28 AM

Go Live without BOM/Routing

46 Views

Hi,

We will be going live with some lacs of FG/SFG items. Since business is not able to provide BOM/Routing for all the materials, what should be the cutover strategy. I have planned as below

1. Put Standard price for all FG/SFG in Planned price 1 field

2. In MRP2, mention procurement type as X for all materials

3. After loading material master, execute costing run. Wherever, system finds BOM/Routing, it will cost based on that and wherever it does not find, it will cost based on Planned price

Will there be any issues with above strategy specailly for below points

1. Since we will be doing Procurement type X for all materials, will it cause any issue in Production for in house materials (Procurement type E). do we need to change the procurement type after costing run

2. With regard to cost component split- For many materials we will not have cost component split (costing based on Planned price), so varaince analysis will be of no use. Though i can still get actual cost component split in ML after month end and same in COPA as well

Please advice what should be the best approach in such a scenario

Thanks and Regards,

Shiv