Related to Preventive Maintenance Performance Based Process

34 Views

Dear Sir,

Currently In my company Preventive Maintenance Process(Performance Based in Hours) is in under implementation Process.

The scenario is as:

Operation Description

Maintenance Package

First Operation (Filter change)

Every 50 Working Hours

Second Operation (Seal change)

Every 100 Working Hours

Third Operation (Lub oil change)

Every 250 Working Hours

Fourth Task (Grease change)

Every 500 Working Hours

Fifth Task (Fuel Filter change)

Every 1000 Working Hours

Step 1: Maintenance Strategy Creation

Maintenance Package Hierarchy given 1, 1, 1, 1, 1.

Step 2: Task List Creation (General Task List)

Maintenance package for Operation Selection(Check Box) ????

Step 3: Create Strategy Plan

Please check and confirm the Process is correct or not.

Please resolve my problem.