hi ,

consider 2 examples i am doing make to stock and make to order process,

Make to stock

1. fg 1

2. sfg1

3 sfg2

4. rm1

5 rm2

Now in the above case what i should maintain in mrp4 whether individual requirement or collective requirement or individual / collective requirement for fg ,sfg1,sfg2,and rm1 and rm2

Make to order

1. FG2

2. SFG1

3.SFG3

4.RM1

5. RM3

Now in the above case what i should maintain in mrp4 whether individual requirement or collective requirement or individual / collective requirement for fg ,sfg1,sfg2,and rm1 and rm2. Now in both the cases fg is different one is make to stock and another is make to order and sfg1 and rm1 used as component in make to stock and make to order also. Please explain what is the implication of this field and how to test it for fg and sfg and rm