Hi Gurus,
I have a problem where, on MD04, I have a Dependent Requirement (DepReq) for a raw material that no longer has a parent planned order. And with each new run by the MRP, the DepReq is not eliminated as it should.
I now know that the solution for this particular problem is to implement SAP note no. 633119 which states the following:
"In this case, the parent planned order has been deleted but the
dependent requirement still exists. The planned order number is
displayed in the MRP element data of the dependent requirement, but
the planned order itself cannot be displayed or changed. Attempting
to do this generates the error message 61 003, 'Planned order ... does
not exist'."
So far so good, but I still need to find other cases where this also happens. I tried to get some DepReqs through the RESB table but this way is not very effective because of the large quantity of data.
Is there a better way for me to get a few more examples of this situation, DepReqs that are still shown in MD04 but that their Planned Orders are no longer in the system ?
Thanks in advance,
Kind Regards.