Actual Vs planned time in production orders

2249 Views

Dear all,

How do I get a reporting of the actual and planned time for operations in a production order?

Assuming that planned time is maintained in the routing, how do we calculate the actual time that we get from the COOIS in order to compare to the planned time?

1) In the routing we maintain the following standard values:

a. - Setup

b. - Machine

c. - Labor

Operations are confirmed via CO11N and CO19. How can we compare the planned and actual time for the above 3 std values. (For both Tcodes)?

2 2) If I get the total hours in a confirmation for an operation, how do I dispatch this time for the 3 std values (setup, machine, labor)?

Thanks in advance

Suresh