Hi All,
This issue is with Operation Confirmation(CO11). I am having 2 operations 10,20. 10 is the first one to go, and I did a confirmation for yield of 80 EA and Scrap of 20 EA. Then while doing confirmation for the operation 20, I did it for 90 EA and 10 scrap. And system allowed me to post with a yield of 90 quantity.
One more part is, if I am having Back Flushing on for the Operations, and the same above case repeats again, I want component quantity being issued in Operation 20 to be adjusted according to the Yield given by the Operation 10.
In OPK4 we can set the Operation Sequence, I am not sure if this can be of any use. And in case if I am not sure what Operation sequence will be followed(User can confirm any Operation First), I still want component quantity Constraint to be followed.
Please let me know what exactly is needed to be done.
Regards,
Avinash.