Dear Gurus
We have below scenario in Subcontracting where we want to consider Component provided to Vendor in MRP:
- Total stock of X Material 200 nos. is available.
- Requirement generated for 80 nos. of Y Material for which 100 nos. of X material is required.
- 100 nos. of X material provided for creating 80 nos. of Y material.
- Vendor consumes only 95 and creates 80 nos. of Y material. 5 nos remain pending with Vendor.
- Now we run MRP again for Y material for 160 nos. requirement.
- Component requirement generated for X material – 200 nos. out of which 100 is available in Plant stock which gets considered.
- Also 5 nos. left out with Vendor should also be considered while MRP run and actual requirement should have been generated for 195 nos. of X material.
Step 7 is not working i.e. quantity available at Vendor Location which is not blocked for other requirement should have been considered in MRP run for this requirement.
Thanks in Advance