In the below scenario, how can we move the scheduled dates in CM01 for capacity planning?
1. All operations for Work Center INSTRU
operation 0010 - 10 hours, 1 person Start Date: Oct 1
operation 0020 - 5 hours, 1 person Start Date: Oct 2
operation 0030 - 10 hours, 1 person Start Date: Oct 3
2. Confirm 5 hours on Operation 0010, Operation 0010 is now PCNF
3. A part needed in order to complete Operation 0010, 0020 and 0030 is delayed and won't be here for 3 weeks.
4. How do we move all the capacity in CM01 to the week of Oct 22 for all 3 operations. Should show:
operation 0010 - 5 hours, 1 person Start Date: Oct 22
operation 0020 - 5 hours, 1 person Start Date: Oct 23
operation 0030 - 10 hours, 1 person Start Date: Oct 24