Not able to create production order - error: fiscal year variant Y1not manitaned for the calandar year 2030

Former Member
0 Kudos

Hi,

While trying to create production order, getting error that "fiscal year variant Y1not manitaned for the calandar year 2030"

Please adivise.

Thanks,

Suresh.

Accepted Solutions (0)

Answers (4)

Answers (4)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Message no is FGV002?

Please take help of your FI consultant and refer note 6556 to maintain fiscal year variant for the calendar.

Also refer this link,

http://scn.sap.com/thread/1186707

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Suresh,

Pls check your MMPV & MMRV tcodes also in it check your previous year & current year.Then you can maintain FY variant for 2030 FY with taking help for FI Consultant.

Creating Fiscal Year Variant  : 

First Screen (Creating Fiscal Year Variant) .. Continuing …..

Menu Path :     IMG Menuà Financial Accounting à Financial Accounting Global Setting  à Fiscal Year à Maintain Fiscal Year Variant

T-Code :           OB29

check below link which give u guide of maintaining FY variant.

http://www.hareshpradhan.com/sap/sap%20notes6.htm

Check & Revert.

Hope it will help you to resolve ur issue.

TnX

Former Member
0 Kudos

Hi Hrishi,

I am trying to create a production order manually.......so thr is no planned order......i put the start date as 10/30/2012.

Thanks

Suresh.

former_member188931
Active Contributor
0 Kudos

Hi,

Please check the order start date in the planned order 'Display/Change' mode. It should be in 2030.

For this no entry has been maintained for year 2030.

Please check with FI consultant to maintain fiscal year up to 2030. Or check the below link

http://help.sap.com/saphelp_40b/helpdata/es/95/e42c7dd435d1118b3f0060b03ca329/content.htm

Please check and revert.

Thanks

Hrishi

Former Member
0 Kudos

Hi Hrishi,

I am trying to create a production order manually.......so thr is no planned order......i put the start date as 10/30/2012.

Thanks

Suresh.

former_member188931
Active Contributor
0 Kudos

what is the finish date?

Former Member
0 Kudos

I am getting error while entering the operations start date 10/30/2012 and end date also 10/30/2012.

Thanks.

former_member188931
Active Contributor
0 Kudos

Check in the Header material master, whether you have maintained the Period indicator P in MRP3 and also check the if nay entry maintained for Fiscal year variant. If yes, then changed to M and try.