Hello.
Could you give me a solution following question?
I already set MRP1, 2 view of material master.
Lot size : WB(Weekly lot size)
Rouding value : 100 EA
Required quantities are...
Mon : 100
Tue : 30
Wed : 100
Tur : 60
Fri : 20
Total Quantity is 310 EA this week.
Container quantity is 100 EA. So, we should order 400EA.
I want to get 400EA in this week PR.
But, MRP proposed 300 EA. (I set rouning value 100)
How can I set MRP data?
Please, help me.