Oct 29, 2012 at 12:49 PM

MRP Lot size & Rounding value setting

72 Views

Hello.

Could you give me a solution following question?

I already set MRP1, 2 view of material master.

Lot size : WB(Weekly lot size)

Rouding value : 100 EA

Required quantities are...
Mon : 100
Tue : 30
Wed : 100
Tur : 60
Fri : 20

Total Quantity is 310 EA this week.


Container quantity is 100 EA. So, we should order 400EA.

I want to get 400EA in this week PR.

But, MRP proposed 300 EA. (I set rouning value 100)

How can I set MRP data?

Please, help me.