Skip to Content
0
Former Member
Oct 26, 2012 at 10:51 AM

Actual cost is considering in (KP06 / KSPI / KP26)

244 Views

Dear Experts,

We are doing the following:

1, Updating the Plan Activity in KP26 ( cost center & activity type Combination)

2, Updating the Plan figures in KP06 planning ( Cos center/Activity type/Cost Element)

3,KSPI for the plan price calculation ( Plan cost in KP06 devided by Plan Activity in KP26)

We have not maintained any splitting structure as there is only one activity.

The problem is:

While calculating the KSPI, The system is considering the actual cost in the cost center in addition to Plan cost maintained in KP06.

For Example:

Cost center : A is having plan value of Rs.10,000 and actual cost of Rs.2,000

Plan Activity in KP26 is 1000 minutes.

KSPI : Price calculation :

I need 10,000 divided by 1,000 units so the price per unit is Rs.10

System is showing Price per unit Rs.12 (12000/1000)

Please suggest me how to arrive only plan cost.

Regards,

Jyoshna