Is there a way to change activity times recalculate based on the yield quantity in PI sheet ? In COR6 system automatically recalculates the activity times based on the quantities, for example if machining time is an activity that is captured during process order phase confirmation which depends on yield quantity. If user performs partial confirmations system adjust machining time based on the yield entered.

I proposed navigating to COR6 transaction, however, business wants to enter activity time on PI sheet rather navigating to COR6.

Any help is highly appreciated. This will avoid lot of manual work on shop floor.

Many thanks!