I am configuring SAP ABAP Jobs through Redwood .A job has multiple
steps . In SAP, for every step , you do not need to create the job for
every step. But What I see in Redwood , We need to create the job for
every step and also to avoid any confusion we need to append something
_1 or _2 etc .

So when I need to check the logs we need to check the logs of every
step when job is scheduled through Redwood . So can we have anything
in Redwood through Which we can also display the job like SAP.
I short , I just the display of jobs through Redwood is also same as SAP. For multiple steps also ,
there should be one job displayed in SAP where the logs of every steps are stored in single job.

Can we have the answer guys.

- Harshwardhan Kumar

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi - In CPS if you want multiple jobs to appear under a single job, create a Job Chain, and create as much as steps you want under that. You can also define the sequence of the job execution, you can execute all the jobs under a job chain together or they can be dependent.

Thanks

Anil

Former Member
0 Kudos

Anil - Currently I am doing that way only as you explained. But the problem is what , suppose we have for any job 10 steps. So first of all in SAP in SAP , what we see, the job logs of all the steps are under only one job and for every step we do not create the separate job.

In Redwood, yes it is true we can make the job chain, but when you see the logs of same job chain in SAP, you will find for every step a separate job has been created in SM37( SAP) and also if you want to  see the job log in sm37 in SAP , you have to click on every job ( every step in this case 10 step) .