We know that SAP accept the confirmation with any of qty values like Yield,Scrap or Rework, but in our case, when we check the operation confirmation details, system accepted with Zero qty for all. All of yield, scrap and rework qty values are zero. How this is happened? Is there any setting to restrict this? We want to restrict the user to confirm the operation with zero qty for all of yield, Scrap and Rework. We already set under/ over delivery setting, that was working fine. We have to know about the restriction settings for zero qty confirmation.