cancel
Showing results for 
Search instead for 
Did you mean: 

Collective order schedulling: current date planning

Former Member
0 Kudos

Dear all:

We are facing the following issue on our collective order scheduling.

We have the current date scheduling type, on our collective order.

The result is as follows, considering that the main order is 71511485.

Order           Sched start      Sched finish

71511485     30.11.2012     05.12.2012

71511475     29.10.2012     30.11.2012

71511476     29.10.2012     30.11.2012

71511477     29.10.2012     30.11.2012

71511478     24.10.2012     30.11.2012

71511479     20.11.2012     30.11.2012

71511480     20.11.2012     30.11.2012

71511481     20.11.2012     30.11.2012

71511482     20.11.2012     30.11.2012

71511483     20.11.2012     30.11.2012

71511484     29.10.2012     30.11.2012

This is fine considering the whole production order, the first order is being started today (71511478) and all routing times are being considered fine in order to determine the outline dates.

But if we consider the depending production orders, they are being backwards scheduled from the requirement date of the main order.

Our customer requirement is to have today as the scheduled start date.

This is weird as they also have the 'current date' scheduling type.

On OPU3, we have the adjust dates parameter as 2 (do not adjuts basic dates to operation dates) in order to avoid this behaviour, but we are not getting the desired start dates.

Any idea about this issue?

Help will be much apreciated.

Regards.

Accepted Solutions (0)

Answers (1)

Answers (1)

sjeevan
Active Contributor
0 Kudos

Did you try changing the Start in the past  to 0 (blank) in OPU3?

Former Member
0 Kudos

Hi Jeevan.

Of course, i forgot to mention that the Start in the past parameter is already blank.

Also, on  Production-->MRP-->Planning-->Scheduling and capacity parameters -->Parameters for determining the basic dates we have deactivated the 'start in the past' indicator for the corresponding plant, even though this should only make some effect on the planned orders.

So, I guess that this is not coming from this point.

In fact, on some tests with given quantities of the collective order, the dependent orders do execute the current date scheduling when system is determining a start in the past date. The problem is that this is an exception being triggered on certain times.

Thanks for the input, anyway.

Any other idea?