Missing Transportation and Shipment Scheduling during Backorder Processing

21 Views

Hi SDN,

when we are running the Backorder Processing in APO system the start date and end date are populating with the current date.

When we checked the data it is missing with Transportation and Shipment Scheduling data.

There are no - Process Goods Issue,Transpor and Process Goods Recpt.

We defined 2 days for the Transport in our system.

When we are creating a stock transport request in ECC it is creating with all these value sin APO but when we are doing back order processing we are missing with these entries.

Could you please let me know is there any settings missings for the back order processing.