on 10-22-2012 8:39 PM
Dear Gurus,
I have created all plant parameter setting related to MRP and setup the MRP profile for all of materials need to come under that planning. I created a variant using tcode MDBT for screen 1000 to create MRP Run but I am confuse how to run it twice in a day each after 12 hours.
Hi,
Go for batch job that runs every day two times ie.... Morning @ 9AM and Night @ 9PM but I would suggest you go for batch job that schedule to runs every day once which will be in midnight.
Regards,
Biju K
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In MDBT you select your variant and click schedule button,
there you see another button for periodic schedule, click it,
move the radio button to hours and enter 12 and you are done.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
because month is the the first radio button, and the program logic places the radio button to the first place in the group.
Once you have scheduled your job, then you are in a fresh screen to schedule another job, it is not a change or display screen for the just scheduled job.
There is a button on top to display already scheduled jobs. If you click this one and then onto your scheduled job, then you can see the radio button at the right place
User | Count |
---|---|