on 10-21-2012 11:55 AM
Hi Gurus,
We have four raw materials which were handled with V-pricing. however, after the start of the september, I changed their pricing to S pricing. now, when i try to perform single level pricing/closing entries, system gives error c+805 (perform closing entry in previous period). current period is 10 and previous is 9. I thought the possibility of "maybe i close these materials for period 8", even the materials have pricing control V at that period, I tried must_settle and must_close however it gave the same error code.
This is the first time that i changed pricing from V to S and i could not forecast these consequences.
have any ideas?
Hi Mustafa,
RUN THE PROGRAM <MLHELP_SET_PP_STATUS_70>
TDOCE: SE38
This program have to be running 2 times.
This program will set the material status do “70” Closing entry complete.
Than you can perform the single level pricing/closing entries in the current period.
Kind Regards,
Fernando
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.