Factory calender dates

sanju_ms
Active Contributor
0 Kudos

Hi Experts,

While creating the reservation am getting the warning message as per the attached image.

Our working days was 5 days in a week and again changed to 6 days, as per the working schedule I changed the factory calender.

but still getting such warning message ?

Regards,

Sanju  M S

Accepted Solutions (1)

Accepted Solutions (1)

sanju_ms
Active Contributor
0 Kudos

Issue Solved..!

Answers (1)

Answers (1)

tejyadav
Active Contributor
0 Kudos

SAP system compares the Base date & Reqmt Date, If it is different then it issues the Warning message as in your case, Base date you can find at the Initial screen of MB21.Your Base date is generally your current date.