Order Based PPDS Planning Run

Hi Gurus,

Business requirement is when Planned Order is created manually in Product View or DS Board, detailed level planning should carried out for all dependent order and Planned Order should get create automatically for BOM items, not through CDPSB0 or one by one through Product heuristic.

As far as I know such requirement can't be management through CDPS0 transaction, Is there any way to meet the business requirement. Please suggest. Thanks

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Jan 05, 2017 at 07:01 AM

    Hi Mayur,

    Please maintain the Planning procedure as 3: Cover Dependent requirements immediately at BOM Product Location in APO.

    Regards

    Abhinay Kumar