Hi Experts,

I need your help.

if we set up ingredient percentage for a Material(Raw material) in
Master Data(Classification View) when I release the Process Order,
System will create Batch for raw material using Batch determination
process. But system don’t allow to assign Batch have ingredient percentage(Error message:
inconsitancy due to that value was declared in Master
data.)

DO you know how tho correct this?

Thanks.